Removing Hardened Mortar, Grout and Cementitious Deposits from Existing Masonry
Remove the scheduled hardened mortar, grout and cementitious deposits from existing masonry using the treatment system and number of cycles established by the accepted trial.
The button opens an email enquiry. SpecWorks will confirm supply and payment details directly.
how far can
we safely go?
what must the
tenderer price?What it deals with
The technical ground is already organised.
This specification gives the project writer a structured starting point for the operation, while keeping project-specific decisions visible and under professional control.
- Deposit Schedule, Condition Record and Trial
- Protection, Containment and Treatment System
- Removal, Treatment Cycles and Stop Work Conditions
- Inspection, Making Good and Records
Before project issue
Complete it for the project.
Add the locations, quantities, dimensions, materials, interfaces, performance criteria and acceptance requirements needed for the work.
State tender assumptions and separate rates where concealed conditions or materially different work could affect the price. The specification supports professional judgement; it does not replace it.